The State of Wyoming Department of Corrections initially sought hard bids on the construction of the new Medium Correctional Institution in Torrington. When bids came back nearly twice the amount of the original budget, Wyoming officials, contracted with us as GM/GC. We then worked closely through a preconstruction partnership to bring the construction costs within budget.

This difficult site required almost 500,000 cubic yards of sand to be moved and compacted as fill.

Components of the project include prison, administration building, central plant, gatehouse building, warehouse, maintenance building and vocational training. The prison has 720 beds, including infirmary and mental health isolation cells.

Key features include:

  • 720 beds
  • New construction
  • Major soil remediation
  • Central plant